watonomous.github.io

  1. Electrical Division
  2. Electrical Division Home
  3. Power Systems Group

[ Electrical Division : W20 Power Systems EOT Retrospective ]

Created by [ Sidharth Baveja], last modified by [ Mitchell Hoyt] on May 01, 2020

What Went well? 

This term we were able to clean up all of the cabling in the car. This was an extremely important task as at the end of the fall term the new compute rack was put into the car. In addition, we were able to make able to start making progress on an electric test track dummy. 

\

What didn't go well? 

We were not able to really work on the radars. Radars seem to be a task that we continue to drag along a lot unfortunately. Additionally, due to the corona virus we were not really to complete any of the remaining tasks. These tasks include the traffic lights, radars, blue light, test track dummy, etc.  

\

Lessons Learned?

Need to better account for time lost during exams. We lost two to three weeks of development due to exams and reading week. Additionally, due to COVID we lost about one month of development as well. Hence in future terms it is very important that we come up with a better work plan during the exam period. 

 

To do in the meeting tomorrow

\

+—-+——–+———+———————————+———–+ | Ta | Import | Possibl | Plan for tackling this problem | What Can | | sk | ance/I | e | | Be done | | Fo | s | Blocker | | if campus | | r | it | s/How | | is locked | | Ne | critic | we can | | | | xt | al | solve | | | | Te | for | them | | | | rm | compet | | | | | | ition | | | | +====+========+=========+=================================+===========+ | Tr | Critic | COVID: | Have information on different | Planning | | af | al | Plannin | setup of the traffic lights, | for | | fi | - test | g, | started looking into the | integrati | | c | with | reachin | different types of | on, | | Li | actual | g | controllers,  | where the | | gh | traffi | out to | | lights | | ts | c | UofT,  | Mechanical looked into this, | will go | | | lights | | created document for items we | as well | | | ,  | | needed to purchase, talked to | as how | | | | | UofT about assembling lights.  | will they | | | | | | be set up | | | | | Put more research into the need | | | | | | for traffic lights, installing | Looking | | | | | them into the test track, come | more in | | | | | up with a schematic with test | depth | | | | | track infra, integrate the | into a | | | | | placement, what the lanes are | controlle | | | | | located to. elevation of | r, | | | | | lights, #of lights.  | shifting | | | | | | focus on | | | | | \ | the | | | | | | safety of | | | | | | the use | | | | | | of this | | | | | | controlle | | | | | | r.  | +—-+——–+———+———————————+———–+ | Bl | Critic | COVID | Need to wire up the blue light | Nothing,  | | ue | al | | for the inside and install it, | | | li | - | | indoor blue light has been | Reassure | | gh | Needed | | delivered (need to look into if | delivery | | t | for | | this was delivered) | | | | Compet | | | ensure | | | ition | | Place blue light in a more | that it | | | | | visible area | passes | | | | | | the rules | | | | | | | | | | | | NONCRITIC | | | | | | AL: | | | | | | Look into | | | | | | more | | | | | | secure | | | | | | connectio | | | | | | ns | | | | | | for the | | | | | | blue | | | | | | light, | | | | | | provide | | | | | | paragraph | | | | | | s | | | | | | for | | | | | | concept | | | | | | design | | | | | | reports. | | | | | | documenti | | | | | | ng | | | | | | debugging | | | | | | for the | | | | | | blue. | | | | | | | | | | | | \ | +—-+——–+———+———————————+———–+ | Te | Non | COVID | Design is done and documented, | Assure | | st | Critic | | need to test the initial | items got | | Tr | al | | concept and then applying it to | delivered | | ac | - work | | different motors.  | | | k | around | | | Perform a | | Du | for | | | design | | mm | this | | | review on | | y | | | | the | | | | | | system, | | | | | | with 2 or | | | | | | more | | | | | | people | +—-+——–+———+———————————+———–+ | Ra | Non | \ | Ensure that we have plan for | Ensure | | da | Critic | | how we are going to organize | that we | | r | al | | the cables. | have plan | | | - | | | for how | | | radars | | Ensuring a proper and secure | we are | | | aren' | | design for powering the radars. | going to | | | t | | | organize | | | in | | - proper and secure | the | | | comp | | connections | cables. | | | for | | - Simulations, design is able | | | | this | | to power the radars | Ensuring | | | year | | properly | a proper | | | | | - Consider purchasing things | and | | | | | which are able to be placed | secure | | | | | early. Orders take a while | design | | | | | to come in  | for | | | | | | powering | | | | | | the | | | | | | radars. | | | | | | | | | | | | - prope | | | | | | r | | | | | | and | | | | | | secur | | | | | | e | | | | | | conne | | | | | | ctions | | | | | | - Simul | | | | | | ations, | | | | | | desig | | | | | | n | | | | | | is | | | | | | able | | | | | | to | | | | | | power | | | | | | the | | | | | | radar | | | | | | s | | | | | | prope | | | | | | rly | | | | | | - Consi | | | | | | der | | | | | | purch | | | | | | asing | | | | | | thing | | | | | | s | | | | | | which | | | | | | are | | | | | | able | | | | | | to be | | | | | | place | | | | | | d | | | | | | early | | | | | | . | | | | | | Order | | | | | | s | | | | | | take | | | | | | a | | | | | | while | | | | | | to | | | | | | come | | | | | | in  | +—-+——–+———+———————————+———–+ | Ca | Critic | COVID | - Car is properly powered and | look into | | bl | al | | working properly, so the | novatel | | e | - | | compute rack integration is | cables | | Ma | needed | | improved | and how | | na | for | | - Making improvements may | to better | | ge | points | | cause more risks.  | organize | | me | at | | - Improve the novatel cable | them | | nt | compet | | management | | | | ition | | - look into more secure | | | | | | ethernet options | | | | | | - ACU Board redesign look | | | | | | into making this more | | | | | | robust, getting those | | | | | | cables out of the view of | | | | | | the passenger  | | | | | | - Drive crew survey | | | | | | - Judges opinions on this. | | | | | | look into getting further | | | | | | opinions on this | | +—-+——–+———+———————————+———–+

Document generated by Confluence on Nov 28, 2021 22:40