[W20.O1] Dummy rig platform
A test track dummy is needed for software testing in the pedestrian challenge. The dummy will be used for test track and mini-test track days.
[W20.O1.KR4] Build assembly when all parts are available
Assemble all parts according to design on SolidWorks.
0%-->0%
Blockers: Machined part has arrived, off the shelf parts from PO haven’t arrived yet.
[W20.O2] Get lane lines painted on test track
[W20.O2.KR2] Set up meeting with Ross to discuss progress on lane lines.
Email Ross with possible timings and meet to discuss tentative timeline, and required next steps.
0%
Blockers: Ross didnt reply to email. Will try again this dev cycle.
[W20.O3] Getting traffic lights installed at test track
[W20.O3.KR1] Set up meeting with Ross to discuss possible options
Email Ross with possible timings and meet to discuss tentative timeline, required next steps such as contractors to contact etc.
0%
Blockers: Ross didnt reply to email. Will try again this dev cycle.
Group Engagement Rate: (1 - (0 + 0)) / 1 = 100%
Link to engagement level guideline
+:———————-+:———————-+:———————-+ | Name | Engagement Level | Activity Summary | +———————–+———————–+———————–+ | Jackie Bai | Meet | Couldn't do much due | | | | to midterms. Did | | | | whatever was assigned | | | | to him. | +———————–+———————–+———————–+ | \ | \ | \ | +———————–+———————–+———————–+ | \ | \ | \ | +———————–+———————–+———————–+ | \ | \ | \ | +———————–+———————–+———————–+ | \ | \ | \ | +———————–+———————–+———————–+ | \ | \ | \ | +———————–+———————–+———————–+ | \ | \ | \ | +———————–+———————–+———————–+ | \ | \ | \ | +———————–+———————–+———————–+ | \ | \ | \ | +———————–+———————–+———————–+