Created by [ Ardhendu Shekhar Bhattacharya], last modified on Mar 11, 2020
W20.O1] Dummy rig platform
A test track dummy is needed for software testing in the pedestrian challenge. The dummy will be used for test track and mini-test track days.
[W20.O1.KR4] Build assembly when all parts are available
Assemble all parts according to design on SolidWorks.
0%-->100%
[W20.O2] Get lane lines painted on test track
[W20.O2.KR2] Set up meeting with Ross to discuss progress on lane lines.
Email Ross with possible timings and meet to discuss tentative timeline, and required next steps.
0%
Blockers: Ross didnt reply to email. Have escaleated to Rowan.
[W20.O2.KR3] Get in touch with Keenan(UofT captain) to understand how they painted their lane lines
0→ 100%
[W20.O3] Getting traffic lights installed at test track
[W20.O3.KR1] Set up meeting with Ross to discuss possible options
Email Ross with possible timings and meet to discuss tentative timeline, required next steps such as contractors to contact etc.
0%
Blockers: Ross didnt reply to email. Have escalated to Rowan
[W20.O3.KR2] Use available resources to build competition light configuration
0%→70%
Order of traffic lights has been established as doable, mounting will be finished in Dev Cycle 4
\
Group Engagement Rate: (1 - (0 + 0)) / 1 = 100%
Link to engagement level guideline
+:———–+:———————+:—————————————-+ | Name | Engagement Level | Activity Summary | +————+———————-+—————————————–+ | Jackie Bai | Meet | Helped out with traffic light mounting. | | | | | | | | \ | +————+———————-+—————————————–+ | \ | \ | \ | +————+———————-+—————————————–+ | \ | \ | \ | +————+———————-+—————————————–+ | \ | \ | \ | +————+———————-+—————————————–+ | \ | \ | \ | +————+———————-+—————————————–+ | \ | \ | \ | +————+———————-+—————————————–+ | \ | \ | \ | +————+———————-+—————————————–+ | \ | \ | \ | +————+———————-+—————————————–+