[ Knowledge Base : W20.0 Sensor and Compute Mounting EoC ]

Created by [ Chad Kirton] on Feb 06, 2020

Heading

Name: Chad Kirton

Date: February 2nd, 2020

Development Cycle: 0

Division: Mechanical 

Group: Sensor and Compute Mounting

Status

Green

OKR Timeline Progression

[F20.O1] Onboarding

[F20.O1.KR1] CAD and Machining Access

Ensure members have access and understanding of how to navigate and use GrabCAD. Additionally provide members with licenses for SolidWorks. Ensure all members have completed ESMS training to access machining equipment.

Progress: Completed

[F20.O1.KR2] Software Use

Familiarize members with the mechanical workstation and CAD software: SolidWorks, AutoCAD

Additionally, bring members up to speed with previous CAD designs.

Progress: Completed

[F20.O1.KR3] ANSYS Tutorial

Familiarize members with ANSYS Workbench Interface and have them complete a CFD simulation tutorial.

Progress: Completed

[F20.O2] Mounting the Converter to the Compute Rack

[F20.O2.KR1] Requirements

Generate a list of design requirements for mounting the component including component dimensions and mounting hole locations. Additionally, verify compute rack space availability by referring to current CAD.

Progress: Completed

[F20.O2.KR2] Design

Using design requirements, develop a design for method of mounting the converter to base 

Progress: In progress

[F20.O2.KR3] Source Material/ Components

Generate PO of material or off-shelf components for chosen design ( source sponsorship for funding available ).

[F20.O2.KR4] Machining and Fabrication

Depending on the chosen design, have mounting components fabricated or machined using the ESMS.

[F20.O2.KR5] Installation and Review

Install the converter onto the base level of the compute rack and review its implementation with the electrical team.

Link To Retrospective

https://docs.google.com/document/d/1EMCTPXk2a0SrF4PCI_WBtCWaB_5Osoy4YK9O3vaGcGo/edit#

Core Member Engagement

Group Engagement Rate: (3 - (1)) / 3 = 66.7%

Link to engagement level guideline


Name Engagement Level Activity Summary Matthew Lee Exceed  Member has completed all onboarding tasks and is working on [F20.O2.KR2].  Aryan Trehan  Exceed Member was recruited after Dev Cycle 0 started but has been brought up to speed and completed all onboarding.  Aasif Patel  Meet  Member was unable to attend second half of Dev Cycle due to personal matters ————— ———————- —————————————————————————————————————

Comments:

+———————————————————————–+ | [] | | | | Chad | | Kirton{.con | | fluence-userlink | | .user-mention} | | | | You're Core Member Engagement table is out of sync with the W20 | | Member | | List: <https://docs.google.com/spreadsheets/d/1SIzvoCDtFpwPHrJ4NVhLDy | | FacFDK8tVT1vGiWoa8iLo/edit#gid=676905603&range=5:5> | | | | please synchronize them!  | | | | {.smallfont align=”left” style=”color: #666666; width: 98%; margi | | n-bottom: 10px;”} | | | | Posted by r2dempst at Feb 12, 2020 22:54 | | | +———————————————————————–+